Bridge Footings and Cased, Georgetown, Tx
JOB DESCRIPTION
FOOTING #1 Drilled 1 – 38″ Diameter Footings @ a Depth of 17′
Drilled 1 – 36″ Diameter Footings to a Final Depth of 19′ w/ 6′ Embedment into Limestone
FOOTING #2 Drilled 1 – 38″ Diameter Footings @ a Depth of 11′
Drilled 1 – 36″ Diameter Footings to a Final Depth of 18′ w/ 6′ Embedment into Limestone
CASING Installed 1 – 36″ x 17′ Pipe Casing and Cleanout w/ Mudbucket (Machined Casing to Add 7 Ft)
Installed 1 – 36″ x 11′ Pipe Casing and Cleanout w/ Mudbucket